September 20th, 2024

Centre Block construction within cost, but Ottawa needs to make faster decisions: AG

By The Canadian Press on March 27, 2023.

Auditor General Karen Hogan leaves after holding a press conference in Ottawa on Tuesday, Dec. 6, 2022. THE CANADIAN PRESS/Sean Kilpatrick

OTTAWA – Canada’s auditor general says the modernization of Parliament’s Centre Block is within budget so far, but the federal government needs to do a better job at making up their minds before major construction begins.

Karen Hogan warns in a report released today that if decision-making remains fragmented, it could lead to construction delays – and more costs for taxpayers.

The rehabilitation of Centre Block already comes with a price tag of up to $5 billion, and is set to be completed by 2031.

Hogan says the government is responsible for deciding what it wants, including how many office spaces, committee rooms and security measures are needed.

She says it’s important for such decisions to be made promptly so construction cost can be determined and the project can be kept on track.

The federal government says in response that it will start submitting project reports to the Speakers of the House of Commons and Senate twice a year, and it has committed to undergo a study to ensure the space is inclusive.

This report by The Canadian Press was first published March 27, 2023.

Share this story:

8
-7

Comments are closed.